Project Schedule

The image below was the proposed Gantt Chart for the completion of the project.

The updated Gantt Chart is presented in the figure below. The scope of the project did not change but drying and sieving took longer than expected, pushing the project tasks back by a week. Additionally, new lab requirements and lab closures also created a delay in the completion of the drying and sieving.